What can a homebuyer do if builder delays flat handover?

What can a homebuyer do if builder delays flat handover?


Play all audios:

Loading...

EXPERT: UDAY WAVIKAR, VP, CONSUMER COURT BAR AND ASSOCIATION. QUESTION: IN 2012 MY SON BOOKED A FLAT IN JAYPEE GREENS, NOIDA.  PROVISIONAL ALLOTMENT LETTER (PAL) WAS ISSUED IN SEPTEMBER


2012. THE POSSESSION WAS SUPPOSED TO BE GET ON MARCH 2016. HE HAS DEPOSITED AROUND RS 50 LAKHS ON THE TOTAL OF RS 65 LAKHS ON THE BASIS OF DEMANDS RAISED BY THE BUILDER TIME TO TIME. NOW


CONSTRUCTION HAS STAND STALLED FOR LAST ONE YEAR. WHAT LEGAL RECOURSE CAN I TAKE TO GET THE FLAT OR FOR REFUND WITH INTEREST? Answer: You can file a case in civil court or consumer court.


Ask builder for possession of the flat. If you want to take refund over the possession is delayed then ask for the current market price of that flat or also you can ask for refund of the


money with interest and compensation. DON'T MISS: WHAT RECOURSE TO AVAIL FOR DELAY IN POSSESSION?